I believe this was the USN portion of the contract.


https://aais.ria.army.mil/aais/award...000/P00001.pdf
https://aais.ria.army.mil/aais/award...1200001/01.pdf


Quote:
SECTION A - SUPPLEMENTAL INFORMATION
The purpose of this modification is to terminate Contract W52H09-08-D-0120 and Delivery Order 0001 to this contract.
This is a no cost mutual termination based Bushmaster's letter dated January 10, 2008 and the SBA size
determination Case Number 01-SD-2008-12 dated 15 January 2008.
The termination will be at no cost to either the Government or Bushmaster Firearms. Thus, the Government,
as represented by the Contracting Officer, agrees that it will not seek to recover from the contractor any
excess reprocurement costs connected with the reprocurement of any items covered under this contract.
Thus, the contractor hereby waives any and all rights and claims for equitable adjustment attributable to
such facts and circumstances giving rise to the above termination and hereby releases the Government from
any and all liability under this contract, including any interest and any claims for delay.
In accordance with the Non-Disclosure Agreements included with the original solicitation at Attachments
002 and 003, Bushmaster Firearms is to provide a certificate of destruction that certifies that the
technical data in the CD-ROM or any other format provided by the US Government under Solicitation
W52H09-07-R-0205 have been destroyed along with any copies in any form (CD-ROM, print, etc.) and
will further certify that no copies in any form whatsoever have been retained.
As a result of the termination by mutual agreement, a modification to Delivery Order 0001 will be
issued to decrease the total quantity and dollar value.
 